GANDERBAL, SEPTEMBER 11: In order to have a firsthand appraisal about the progress on various ongoing development projects, the Deputy Commissioner Ganderbal, Krittika Jyotsna today took whirlwind tour of the district.
During the visit, the DC inspected the progress made on under construction NTPHC Shalabugh, Dak Banglow Fathepur, Medical Oxygen Plant at District hospital, PMGSY road at Bonibagh Kangan and many other ongoing works in the district.
Additional District Development Commissioner, Pir Muzafar Ahmad, SE R&B, Executive Engineers of R&B and PMGSY and other concerned officials accompanied the Deputy Commissioner.
While inspecting the construction of NTPHC Shalabugh, SE R&B briefed the DC about the physical and financial progress on the project and informed that all major works are completed except few minor finishing works including fencing and filling of ground.
The DC directed the SE, R&B that the remaining works should be completed within a week so that the project is inaugurated on time and thrown open for the public.
While inspecting the progress on Dak Banglow Fathepur, which is also executed by the R&B department, the SE informed that the total project cost is Rs 490 lakh which include Rs249.53 lakh of Languishing component and 95 percent physical work is completed till date.
Keeping in view the importance of this prestigious project, the DC directed him to expedite the work progress so that it gets completed within a given timeline.
Earlier, the DC inspected the progress on Medical Oxygen Plant which is being installed at District Hospital Ganderbal.
Hospital authorities informed the DC that the Oxygen concentrator plant is being established under PM Care Fund with 1000 LPM capacity.